Re: This may not a related question to SQR
- Subject: Re: This may not a related question to SQR
- From: Anne-Marie Matula <amatula@OIT.UMASS.EDU>
- Date: Thu, 22 Jun 2000 09:02:45 -0400
- Importance: Normal
- In-reply-to: <200006220600.AAA17314@list.iex.net>
More info on this:
Go to the Process Scheduler in PS. Add a Job Definition that runs the 3
processes you mentioned in the correct order.
Hope that helps... I suspect however things may be complicated than I infer
from reading your post! Good luck!
Have a great day!
Anne-Marie
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
Anne-Marie Matula
Student Information System Project
Office of Information Technologies
University of Massachusetts
161 Whitmore Administration Building
Amherst Massachusetts, 01003-8165
Phone: 413/577-0685
Fax: 413/545-2150
> Date: Wed, 21 Jun 2000 11:38:01 -0700
> From: "Peter R. Lewandowski" <peter.lewandowski@CSUN.EDU>
> Subject: Re: This may not a related question to SQR.
>
> Did you look into using Process Groups within PeopleSoft? It
> creates some dependency.
>
> Date sent: Wed, 21 Jun 2000 14:11:32 -0400
> Send reply to: sqr-users@list.iex.net
> From: "PHUNG, BINH" <BPHUNG@FINEHOST.COM>
> Subject: This may not a related question to SQR.
> To: SQR-USERS@list.iex.net
>
> > I am using PeopleSoft7.52 on NT with SQL7.0.
> > Currently we are using the EDI Manager to input vouchers into
> PeopleSoft.
> > There are three steps: step1 is an sqr and it reads the Input file and
> > writes it out to an Output file formated for Step 2. Step 2 is
> also an sqr
> > and was developed by PS. It reads the output file from step 1
> and pushes it
> > to the staging table. The third step is a PSJOB class which posts or
> > something like that.
> > My question is can i automate these steps to be kicked off from one sqr.
> > Have the sqr find the files to be inputed and pass the file name to the
> > steps. Or do i have to insert the filename into the fields of the steps?
> > I plan to use the process scheduler to schedule the main sqr.
> > Any hint and ideas would be great.
> > TIA
> > Binh
>
>
> Pete Lewandowski
>